Permit: E 20191137 Flags:   NO 
Description: ELECTRICAL PERMIT 
Project: FOUR SEASONS KOELE  
LANAI RESORTS, LLC
Status: DONE  Entered: 30-May-2019 
Issued: 30-May-2019  Completed: 27-Nov-2019 
Decision:
Expiration:   Last Renewal:  
Location Desc.:  

Parcel Information
Address TMK  
 1 KEOMOKU HWY   2490180010000     GIS Parcel

Scope of Work
Project: FOUR SEASONS RESORT LANAI, KOELE

Scope: ELECTRIC VEHICLE CHARGERS - SOUTH PARKING LOT.

ELECTRICAL WORK INCLUDES NEW PANEL 'EVS' IN BUILDING 'SOUTH PLANT' - FED BY MAIN SWITCHGEAR VIA NEW 150-KVA TRANSFORMER - FOR 12 TESLA VEHICLE CHARGERS IN SOUTH PARKING LOT.

Fee Summary: 1 feeder 200-400a, 1 xfmr > 100kva, 12 misc circuit

Project Electrical Engineer: KAREN A. MARTINEZ, PE 16927-E

 


Professionals / Contractors
WASA ELECTRICAL SERVICES INC as PRIME
861 EHA STREET Phone:
WAILUKU, HI 96793
C13 - ELECTRICAL
License: 0010008 Expires: 30-Sep-2022
CRAIG H MURAKAMI as PROJLEAD
Phone:
,
EJ - JOURNEY WORKER ELECTRICIAN
License: 0004178 Expires: 30-Jun-2023
KAREN A MARTINEZ as ELEC ENGR
Phone:
,
EE - ELECTRICAL ENGINEER
License: 16927 Expires: 30-Apr-2020

[QUANTITIES]
Structure Classification
Initial Value: $0.00  Calculated Value: $0.00 
Standard Plan:   Public Project:  
# of Structures:    # of Res. Units:   
Total Floor Area:   
Model:    

Occupancy Group Construction Type Structure Class
None attached.
None attached.
None attached.

Inspections
Inspection Result Completed Date Completed By Schedule
CORR
N
O
C
E4 - ELEC FINAL PASS  27-Nov-2019  CKELE  26-Nov-2019  Y
E2 - ELEC ROUGH-IN COMPLETE DEVICES & LUMIN PASS  12-Nov-2019  CKELE  12-Nov-2019  N
E1TR - ELEC CONDUITS IN TRENCH PASS  12-Nov-2019  CKELE  12-Nov-2019  Y

   
Activities
Description Assigned Nodes Dur. Est. Completion Target End Decision Decision Date
Beg End
There are no activities for this application.

Permit Flags
Flag Description Status
There are no flags on this application